Water Plant No. 3 - Silverlake/Silvercreek, Brazoria County MUDs 1, 2, 3, and 6

Jones & Carter, Inc. served as the design and construction management engineer for all three (3) phases of Water Plant No. 3.

Phase I included a 700,000-gallon composite elevated storage tank (EST) on a new site. Single-family homes were constructed near and around the EST within the next year.

Phase II included a 620,000-gallon welded steel ground storage tank, a 15,000-gallon hydropneumatic tank, three (3) 1,250-gpm booster pumps, a 2,100-gpm well, plant piping, controls, and electrical. Phase 3 included a 620,000-gallon welded steel ground storage tank, a 15,000-gallon hydropneumatic tank, two (2) 1,250-gpm booster pumps, a 600-kilowatt generator with sound attenuation and fuel containment, plant piping, controls, and electrical.

Phase III included a 620,000-gallon welded steel ground storage tank, a 15,000-gallon hydropneumatic tank, two 1,250-gpm booster pumps, a 600-kilowatt generator with sound attenuation and fuel containment, plant piping, controls and electrical.

Smart Engineering. Smart Solutions.™ © 2009 Jones & Carter, Inc.